HomeMy WebLinkAbout603 PZ 26 Comp Plan Appendix 7A UV
603 PZ 26
PZC
LINCOLN COUNTY PLANNING & ZONING COMMISSION
STAFF REPORT
Plan Amendment Proposal
HEARING TIME AND DATE: 6:00 p.m., November 18, 2026
LOCATION: Lincoln County Courthouse, Commissioner Boardroom 3rd Floor, 925 Sage Ave.,
Kemmerer, Wyoming & Afton Planning & Development Office, 61 E. 5th Ave., Afton, Wyoming
FILE # 603 PZ 26
APPLICANT: Lincoln County Planning & Development Office
PROJECT NAME: Comprehensive Plan Update Appendix 7.A. Upper Valley Transportation
Alternatives Plan
PLANNER: Katie Gipson
____________________________________________________________________________________
PROPOSAL: A Proposed Plan Amendment to the Lincoln County Comprehensive Plan to replace
portions of Appendix 7.A. Star Valley Trails and Open Space and adopt the Lincoln County Upper
Valley Transportation Alternatives Plan.
___________________________________________________________________________________
ATTACHMENTS:
1. Lincoln County Upper Valley Transportation Alternatives Plan
2. Summary
___________________________________________________________________________________
PLANNING STAFF RECOMMENDATION:
Planning Staff recommends that the Planning and Zoning Commission make a motion to approve
a 30 day public notice to consider adoption of File # 603 PZ 26.
This page has been left intentionally blank.
The draft Upper Valley Transportation Alternatives Plan (TAP) was prepared for Lincoln County, Wyoming by Avenue Consultants with planning support from Sunrise Engineering, the Steering Committee, and local staff.
&
01
TABLE OF CONTENTS
02
03
04
A
B
C
D
EXECUTIVE SUMMARY ....................................................................................1
Executive Summary ...............................................................................................................2
EXISTING CONDITIONS ..................................................................................5
Overview ..................................................................................................................................6
Review of Existing Plans & Infrastructure ........................................................................6
Population & Land Use Patterns ........................................................................................9
Crash & Safety Analysis .....................................................................................................12
Origins & Destinations Analysis .......................................................................................15
Bicycle Level of Service .....................................................................................................16
Identification of Barriers & Gaps .....................................................................................20
Key Findings & Next Steps ...............................................................................................23
COMMUNITY OUTREACH ............................................................................25
Public Survey .......................................................................................................................26
In-Person Outreach ............................................................................................................27
CONCLUSION ................................................................................................29
Final Recommendations....................................................................................................30
Implementation & Funding Strategy ..............................................................................34
APPENDIX A - PROJECT CONCEPTS ..........................................................43
APPENDIX B - COST ESTIMATES .................................................................53
APPENDIX C - INTERSECTION DESIGNS ....................................................65
APPENDIX D - CONCEPT LAYOUTS ............................................................69
This page has been left intentionally blank.
01
EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
THE PLAN AT A GLANCE
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
2
The Upper Valley Transportation Alternatives Plan (TAP) establishes a long-term vision for improving walking and bicycling throughout the communities of Afton, Auburn, Fairview, Grover, Osmond, and Smoot. The plan was developed through a combination of technical analysis, stakeholder collaboration, and community outreach, including an online survey that received 173 responses from residents across the Upper Valley.
The planning process found that existing sidewalks, trails, and marked crossings are concentrated primarily within Afton, while many surrounding communities have limited active transportation infrastructure. Analysis of destinations, crash patterns, bicycle comfort levels, and community feedback identified a need for safer and more connected routes between communities, schools, parks, businesses, and recreational destinations. US-89 emerged as both the most important transportation corridor in the valley and one of the most significant barriers to walking and bicycling.
Figure 1.1. Proposed AT Projects for the Upper Valley
To address these needs, the plan recommends a valley-wide active transportation network consisting of approximately 83 miles of improvements, including 51 miles of shared-use pathways and 32 miles of roadway shoulder improvements (see Figure 1.1 below). The plan also identifies 11 recommended crosswalk locations and 5 potential underpasses to improve safety and connectivity at key roadway crossings. Concept-level designs and planning-
level cost estimates were developed for
approximately 16 miles of priority projects and
two key crossing locations to help position
communities for future funding opportunities,
see Chapter 3 for additional details.
Together, these recommendations provide a roadmap for creating a safer, more connected active transportation network that enhances mobility, recreation, and quality of life throughout the Upper Valley. This plan may be used to support grant applications, coordinate with WYDOT, advance survey and design, evaluate right-of-way, and phase projects into capital programs.
EXECUTIVE SUMMARY
3
This page has been left intentionally blank.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
4
02
EXISTING CONDITIONS
EXISTING FACILITIES
REVIEW OF EXISTING PLANS & INFRASTRUCTURE
As part of the initial existing conditions analysis, the project team used high-resolution aerial imagery to identify and digitize existing active transportation facilities into a comprehensive GIS database. This effort established a baseline understanding of current pedestrian and bicycle infrastructure throughout the Upper Valley study area. The resulting mapping shows that formal active transportation facilities are concentrated almost entirely within the Town of Afton. The primary exception is the paved trail along US-89 that extends beyond the Afton town limits to County Road 146.
All marked crosswalks within the study area are located within the Town of Afton, and there is currently only one marked crossing of US-89, located near the center of town between 4th and 5th Avenue. In total, the Upper Valley includes approximately 3.8 miles of paved paths or shared-use trails, 13.1 miles of sidewalks, and 17 marked crosswalks. These findings highlight the limited extent of existing active transportation infrastructure outside of Afton and underscore the need to evaluate opportunities for improving connectivity between communities and across key corridors within the Upper Valley.
STAR VALLEY TRAILS & OPEN SPACE PLAN (2005)
The Star Valley Trails and Open Space Plan was developed as an appendix to the Lincoln County Comprehensive Plan and was initiated to address the growing need for recreational infrastructure and public land access in Star Valley, Wyoming. The plan’s purpose is to preserve the valley’s character, enhance quality of life, and support tourism through a comprehensive trail system and open space strategy. It outlines a vision for interconnected bicycle and recreation trails utilizing existing public road rights-of-way, utility corridors,
and canal easements, while also addressing access to surrounding federal and state lands. The plan emphasizes adherence to AASHTO standards for bicycle facilities and proposes four types of trail development: bike lanes, striped shoulders, signed routes, and shared-use paths. Recommendations include a major shared-use path along US Highway 89, arterial bicycle routes on state and county roads, and town street connections to link neighborhoods with the valley-wide system.
This chapter summarizes the existing conditions analysis prepared by Avenue Consultants in support of the Lincoln County Upper Valley Transportation Alternatives Plan. The purpose of this analysis is to establish a comprehensive understanding of current transportation, land use, and safety conditions within the study area to inform the development of active transportation recommendations. The Upper Valley project area is defined as the valley extending from County Road 155 at the southern end to County Road 128 at the northern end, encompassing the communities of Smoot, Osmond, Fairview, Afton, Grover, and Auburn, as well as the surrounding unincorporated areas.
OVERVIEW
The existing conditions analysis summarizes the following topics:
»Review of Existing Plans
» Population and Land Use Patterns
»Crash and Safety Analysis
» Origins and Destinations Analysis
» Bicycle Level of Service / Bicycle
Compatibility Index
» Identification of Barriers and Gaps
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
6
Figure 2.1. Existing AT Facilities in Upper Valley
Figure 2.2. Existing
AT Facilities in Afton
Outside Afton, formal active transportation facilities are limited, making inter-community connectivity the central challenge for the plan.
Figure 2.3. Proposed Facilities (bicycle shoulders/paved trails) from the
Star Valley Trails and Open Space Plan (within upper valley/non-local)*
EXISTING CONDITIONS
7
SAFE ROUTES TO SCHOOL PLAN AFTON ELEMENTARY SCHOOL (2012)
EXISTING PLAN & INFRASTRUCTURE SUMMARY
The Afton Elementary School Safe Routes to School Plan was developed in response to safety concerns following the relocation of the school to a new site on the edge of town and a desire to create safe and clear walking and biking routes for students to get to school. The plan identifies barriers to walking and biking, which includes the lack of sidewalks and the various creeks and culverts, which forces pedestrians and cyclists into vehicle lanes, and high-speed state routes. Discussions with Lincoln County School District administrators and observations during the Safe Routes to School Plan (SRTS) revealed that most students currently arrive by bus or car, with very few walking or biking due to these hazards. The plan emphasizes the importance of improving infrastructure to make active transportation a safe, connected and appealing option for students.
This review of existing facilities and prior planning efforts establishes a clear baseline for active transportation planning in the Upper Valley by identifying both current gaps and longstanding community priorities. The concentration of sidewalks, trails, and crossings within Afton, combined with limited infrastructure between communities, highlights the need for strategic investments that improve connectivity along key corridors such as US-89 while strengthening local networks within town centers.
To address these issues, the plan
recommends engineering solutions
including expanding the existing
sidewalk network, improving
intersection control signage to provide
safe crossing locations, and hybrid
beacon crossings along US-89. The
action plan prioritized these strategies
with timelines and funding sources,
aiming to create a safer, more connected
environment for students traveling to
school. The table below shows the
projects that were proposed as part
of the plan and which ones have been
constructed as of January 2026.
Figure 2.4. Afton Safe Routes to School Plan Recommendations
PROJECT DESCRIPTION STATUS
Swift Creek Bridge at Madison St Ped bridge to the west of vehicle bridge along Madison St.Built
Flagstaff Ditch Culvert Extension Culvert Ext Built
Crosswalk at 2nd Ave and Madison St Crosswalk Built
Madison St Pathway Construct a walkway Built
Center St connection to Washington St
Draw bus and vehicle traffic away from ped routes, build road north of school from US-89 to Rockbridge Dr Not Built
Jefferson St Pathway & Bridge Extend over Swift Creek and connect to 1st Ave Not Built
Existing plans consistently emphasize safe routes, shared-use paths, and regional trail connections, reinforcing the relevance of these concepts today. Together, this information helps guide the Transportation Alternatives Plan by clarifying where new facilities can build on prior investments, address documented safety concerns, and advance a coordinated, valley-wide approach to walking and bicycling that is realistic, implementable, and responsive to community needs moving forward.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
8
LAND USE PATTERNS
POPULATION & LAND USE PATTERNS
Figure 2.5. Lincoln County Zoning in Upper Valley
Figure 2.6. Afton City Zoning
89 and surrounding neighborhoods. This land use pattern supports shorter, more frequent trips and creates strong potential for walking and bicycling as viable daily travel modes. As a result, active transportation improvement within Afton can focus on fine-grained connectivity, including sidewalk gap closures, enhanced crossings, and low-stress bicycle facilities that link residential neighborhoods to downtown, schools, parks, and civic destinations. Together, the county and municipal zoning frameworks highlight the need for a layered approach to active transportation planning, one that balances regional corridor connections through rural areas with more detailed, pedestrian-oriented networks within town centers to support safe and convenient travel throughout the Upper Valley.
Review of the county zoning and zoning within the Town of Afton provides important context for how and where active transportation investments can be most effective in the Upper Valley. At the county level, most land in the valley is zoned for rural and agricultural uses, with pockets of public, recreation, and mixed-use zoning concentrated around community centers. These patterns indicate longer travel distances between destinations outside of town centers, reinforcing the importance of safe, comfortable connections along key corridors, particularly US-89 to accommodate longer distance trips. Active transportation facilities in these areas should prioritize regional connectivity, shared-use paths, and shoulders or separated facilities that accommodate bicyclists and pedestrians traveling longer distances between towns, schools, parks, and services.
Within the Town of Afton, zoning is more compact and diverse, with central business, general commercial, mixed-use, and higher-density residential districts clustered along US-
EXISTING CONDITIONS
9
POPULATION & DEMOGRAPHICS
The resulting density patterns show higher
concentrations of residents in and around
the Town of Afton, with smaller but notable
population clusters in Smoot, Osmond, Grover,
and Auburn. These areas align closely with key
community destinations and services, as well
as with the corridors most frequently identified
by residents through the community survey
as important for walking and bicycling. Taken
together, the population density analysis,
survey input, and destination mapping provide
a consistent and intuitive framework for
prioritizing active transportation connections,
particularly along US-89 and within town
centers, where facilities can serve the greatest
number of people and support existing travel
behavior throughout the Upper Valley.
The map on the following page illustrates
normalized population density across the Upper Valley using data from the 2020 U.S. Census. Population counts were normalized by acreage to more accurately reflect relative density patterns across the largely rural study area and to identify locations where concentrations of residents may generate higher demand for walking and bicycling. This approach helps distinguish between sparsely populated agricultural areas and more compact residential areas within and adjacent to incorporated communities, allowing for a clearer understanding of where active transportation investments can have the greatest impact.
Figure 2.7. 2020 Census - Population Normalized by Acres
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
10
POPULATION & LAND USE SUMMARY
Together, the zoning and population density analysis provides a critical foundation for prioritizing active
transportation investments in the Upper Valley by identifying where walking and bicycling infrastructure
can serve the greatest number of people and support the widest range of daily trips. By layering
land use patterns with normalized population density, this analysis highlights locations where higher
concentrations of residents, and clusters of destinations create strong demand for safe, comfortable,
and convenient active transportation facilities. Focusing investments in these areas ensures that limited
resources are directed toward projects with the highest potential to improve access, safety, and mobility
for residents of all ages and abilities.
Based on this analysis, the land uses and population patterns best served by active transportation include:
» Central Business and Commercial Districts
(Afton CBD, GC, and MCI zones): These areas concentrate jobs, services, retail, and civic destinations, generating frequent short trips that are well suited for walking and bicycling. Enhanced sidewalks, crossings, and low-stress bicycle facilities in these districts can directly support daily travel and local economic activity.
»Higher-Density Residential Areas (R-2 and R-3 districts): Compact residential neighborhoods produce consistent walking and bicycling demand, particularly for trips to schools, parks, downtown, and transit or regional corridors. Improving neighborhood connectivity reduces reliance on vehicle trips and supports safe travel for families, seniors, and youth.
» Mixed-Use and Incorporated County Areas:
County-level mixed zoning areas closely align with the most densely populated census blocks, reinforcing their role as activity nodes outside of Afton. Active transportation connections between these areas and nearby towns can support inter-community travel and recreational access.
» Recreation and Public Lands Near Population Centers: Parks, trails, and recreation areas located near towns benefit from safe, non-motorized connections that support both everyday use and tourism-related travel, particularly along US-89 and other key corridors.
By prioritizing active transportation facilities that connect these land uses and population centers, the Upper Valley Transportation Alternatives Plan can maximize community benefit, improve safety along key corridors, and support both local and regional mobility needs while respecting the valley’s largely rural context. Projects directly serving dense residential areas, schools, parks, and town centers should core higher for near-term implementation.
EXISTING CONDITIONS
11
Crash data for the Upper Valley study area was provided by the Wyoming Department of Transportation (WYDOT), and a five-year analysis period was evaluated from January 1, 2020 through December 31, 2024. To ensure that crash patterns immediately adjacent to the project study area were captured, a 2,500-foot buffer was applied beyond the extents of County Road 155 and County Road 128. This approach allows for a more comprehensive understanding of safety conditions that may influence corridor operations and inform future transportation and safety recommendations.
Over the five-year period, a total of 500 reported crashes occurred within the buffered study area, indicating notable safety considerations throughout the Upper Valley. Crash data were reviewed to identify trends related to severity, collision type, and involvement of vulnerable road users. The accompanying figures illustrate the spatial distribution of crashes by severity (property damage only, possible injury, suspected minor injury, suspected major injury, and fatal), the manner of collision (such as single vehicle, angle, rear end, etc.), and crashes involving bicyclists or pedestrians.
CRASH & SAFETY ANALYSIS
Collectively, these maps identify locations with elevated crash frequency and severity and provide critical context for evaluating existing safety conditions and prioritizing mitigation strategies associated with planned active transportation improvements. In particular, US-89 emerges as a primary corridor of concern, accounting for approximately 66 percent of all reported crashes in the Upper Valley during the five-year analysis period. The crash density (heat) mapping shows notable concentrations of crashes in and around Afton, as well as in the communities of Grover and Osmond, and near the curve in the roadway close to County Road 128.
While many of these crashes may not directly involve bicyclists or pedestrians, the observed patterns highlight locations where heightened attention to roadway design, speed management, and intersection and crossing treatments will be especially important. These findings underscore the need to incorporate enhanced safety measures for active transportation users, such as separated facilities, improved crossings, and visibility enhancements, along US-89 and at key community access points to ensure that future investments address existing safety challenges and reduce risk for all roadway users.Figure 2.8. Crash Severity in Upper Valley
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
12
Figure 2.9. Manner of Collision in Upper Valley
Figure 2.10. Crash Density in Upper Valley
Figure 2.11. Bicycle & Pedestrian Involved Crashes in Upper Valley
EXISTING CONDITIONS
13
CRASH & SAFETY SUMMARY
The crash analysis confirms that US-89 is the primary safety concern in the Upper Valley and must be a
central focus of active transportation planning. With roughly two-thirds of all crashes occurring along this
corridor, any pedestrian or bicycle facilities and crossings must be carefully designed to address traffic
speeds, access points, and documented crash patterns. While most crashes do not involve vulnerable
users, the concentration of incidents near Afton, Grover, and Osmond highlights locations where active
transportation improvements require particular attention. These findings reinforce the need for well-
planned, context-sensitive solutions along US-89 to improve safety for all users and guide priorities
in the Transportation Alternatives Plan. Additionally, the crash analysis supports both separation from
traffic and careful crossing design, rather than only route selection.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
14
ORIGIN & DESTINATION SUMMARY
This origins and destinations analysis helps translate land use and community input into actionable priorities for active transportation planning by identifying where people are most often trying to go. By mapping both formal community facilities and locally identified destinations, the analysis highlights corridors and nodes with the greatest potential demand for walking and bicycling. The resulting patterns reinforce US-89 as the primary spine connecting communities, services, and daily destinations across the Upper Valley, indicating that improvements along this corridor, along with targeted connections within town centers, will yield the greatest benefit. This information directly informs where active transportation investments can most effectively support everyday travel, improve access to key services, and align with how residents already move throughout the valley.
As part of the existing conditions analysis, Avenue developed a comprehensive GIS database of key community destinations throughout the Upper Valley. This database includes schools, libraries, parks and recreational areas, post offices, the hospital, senior centers, and the temple, all of which represent important daily and recurring trip generators for residents of all ages and abilities. These destinations were mapped to better understand existing land use patterns and to identify opportunities for improving multimodal connectivity within the valley.
ORIGINS & DESTINATIONS ANALYSIS
COMMUNITY SURVEY DESTINATION RESULTS
In addition to mapping established community facilities, the public survey conducted as part of this effort asked residents to identify specific destinations they regularly travel to within the Upper Valley. Survey responses highlighted both formal and informal destinations that may not be captured through standard land use datasets but nonetheless play an important role in local travel behavior. These community-identified destinations were digitized and incorporated into the GIS database to ensure that local knowledge and travel needs were fully represented in the analysis.
A destination density heatmap was then generated to visualize concentrations of key trip generators and to identify corridors with the greatest potential demand for active transportation connections. This analysis further reinforces the importance of US-89 as a primary spine connecting communities and destinations throughout the Upper Valley and underscores its role as a priority corridor for future pedestrian and bicycle infrastructure improvements.
Figure 2.12. Destinations
EXISTING CONDITIONS
15
To evaluate bicycling comfort and stress on roadways in Lincoln County, the project team developed a planning Bicycle Level of Service (BLOS) model using a GIS based approach. The BLOS is based on the Highway Capacity Manual (HCM) framework, but it was adapted and calibrated to better reflect rural roadway conditions, limited data availability, and local conditions of the county’s transportation network.
The analysis focused on roadway characteristics that most strongly influence how comfortable or
stressful a road feels for people riding bicycles. These include traffic volumes, vehicle speeds, the
presence of heavy vehicles, available shoulder width, and pavement condition. Each roadway segment receives a numeric BLOS score, which is then grouped into standard LOS grades ranging from A (very comfortable) to F (unsuitable).
BICYCLE LEVEL OF SERVICE
DATA & GIS INPUTS
Most of the roadway inputs used in the BLOS calculation came from the 2024 Highway Performance Monitoring System (HPMS) dataset for Wyoming. Specifically, on US-89 and other select routes HPMS provided:
» Average Annual Daily Traffic (AADT)
» Heavy vehicle (truck) percentages
»Posted speed limits
» Lane and shoulder width information
»Pavement Condition
Because HPMS data are not available for every roadway segment and can sometimes lack detail on shoulder conditions, the dataset was supplemented using additional sources including high resolution six-inch aerial photography from Lincoln County GIS. These images were used to verify and refine shoulder widths and roadway cross-sections where needed. Google Street View was also reviewed for select segments to confirm roadway characteristics such as shoulder usability and speed limits.
Pavement condition data were obtained
directly from Lincoln County and the Wyoming
Department of Transportation (WYDOT).
Pavement ratings were simplified into condition
categories (good, fair, poor, and unpaved) for
use in the BLOS model.
For roadway segments without complete traffic data, AADT and heavy vehicle percentages were estimated based on functional class and nearby observed values. These assumptions were applied consistently across the network to maintain internal consistency. The maps below summarize the inputs used in the BLOS.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
16
Figure 2.13. AADT 2024
Figure 2.14. Truck Traffic Percentage 2024
Figure 2.15. Posted Speed Limits
EXISTING CONDITIONS
17
Figure 2.17. Pavement Condition
Figure 2.18. Bicycle Level of Service
Figure 2.16. Paved Shoulder Width
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
18
BLOS CALIBRATION AND RESULTS SUMMARY
Initial application of standard HCM-style BLOS coefficients produced results that did not accurately reflect observed bicycling conditions on rural roads in Lincoln County. Default coefficients tended to penalize low speed roads, underrepresent benefits of paved shoulders for cyclists, and cluster the majority of roadway segments into a narrow range of LOS outcomes of LOS E/F.
To address these limitations, an iterative calibration process was undertaken to adjust selected coefficients while preserving the conceptual structure of the HCM methodology. The calibration focused on (1) re-centering the speed term so that low-speed roads are not automatically penalized, (2) strengthening the influence of effective roadway width to reflect the importance of shoulders in rural bicycling comfort, and (3) Moderating pavement penalties so unpaved and gravel surfaces better represent relative bicycling stress in the local context. The final coefficients were selected based on their ability to produce a realistic spread of LOS grades, clearly differentiate higher-speed and
higher-stress corridors, and maintain intuitive consistency with field conditions and local experience.
Overall, the BLOS results show that many state and county roadways experience higher levels of bicyclist stress due to a combination of high travel speeds, limited or nonexistent shoulders, heavy vehicle traffic, and poor pavement conditions. Lower-stress segments (LOS A–C) are generally concentrated on lower-speed roads and roadways with wider paved shoulders, while higher-stress segments (LOS D–F) are more common on US-89 and other state and county corridors with higher speeds and traffic volumes.
The BLOS map (Figure 2.18) illustrates how these conditions vary spatially across the county and helps identify corridors where infrastructure improvements such as shoulder widening, speed management, or pavement upgrades could significantly improve bicycling comfort and safety. These results are planning-level and intended to support corridor prioritization, not replace detailed design-level safety analysis.
EXISTING CONDITIONS
19
As part of the existing conditions analysis, the project team conducted a barrier and gap assessment to identify missing links in the active transportation network, physical constraints, and safety concerns that limit walking and bicycling throughout the Upper Valley. This analysis builds on field observations, GIS mapping, and a review of existing transportation facilities. Results show that sidewalks and marked crosswalks are located exclusively within the Town of Afton, and the only paved trail extending beyond town limits connects Osmond to Afton along US Highway 89 between County Roads 146 and 145. Extending this trail represents a clear opportunity to improve connectivity, subject to available funding and community priorities.
The accompanying maps illustrate how existing facilities are concentrated in the Afton area and highlights key gaps in the sidewalk network. In coordination with Safe Routes to School planning efforts, school bus stop locations were used to define logical walking routes and identify gaps where sidewalk and crosswalk improvements would provide the greatest
IDENTIFICATION OF BARRIERS & GAPS
benefit. This targeted approach helps prioritize investments and focus limited resources on areas with the highest demonstrated need, while recognizing that lower-volume rural roadways may not require fully paved facilities to support comfortable active transportation.
Several significant barriers further affect the comfort and safety of walking and bicycling in the Upper Valley. US-89 functions as a high-speed, high-volume corridor and presents a major barrier between communities, with only one designated crossing within the Town of Afton. Other regional highways (238, 237, 236, and 241) and County Roads 140, 141, and 135 also experience traffic speeds and volumes that limit safe non-motorized travel. In addition, natural features such as the Salt River and associated wetlands restrict east–west connectivity, reinforcing the need for strategically located crossings and well-designed connections. Together, these gaps and barriers provide a clear framework for prioritizing a corridor driven future active transportation network.
Figure 2.19. Existing Sidewalks & Paved Trails in Afton
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
20
Figure 2.20. Existing Facilities & Network Gaps (sidewalks & crosswalks)
Figure 2.21. Afton - Existing
Facilities & Network Gaps
(sidewalks & crosswalks)
Figure 2.22. Osmond -
Existing Facilities & Network
Gaps (sidewalks & crosswalks)
EXISTING CONDITIONS
21
BARRIERS & GAPS SUMMARY
The barrier and gap assessment shows that active transportation infrastructure in the Upper Valley is limited, unevenly distributed, and constrained by roadway and environmental conditions. Most sidewalks and trails are concentrated in Afton, leaving rural communities without formal facilities and a disconnected network. School focused route analysis helped identify the highest priority locations for improvements, particularly near bus stops and within typical walking and biking distances. Major highways, fast rural roads, and natural features like the Salt River and wetlands further restrict safe east–west and north–south travel. These combined challenges underscore the need for targeted investments that improve safety, close critical gaps, and strengthen connectivity across the valley.
TOP GAPS AND BARRIERS
» Concentration of facilities in Afton and lack of facilities elsewhere.
» High-speed, high-volume highways—especially US-89—that significantly hinder safe walking and bicycling, with only one designated crossing in Afton.
• Other regional highways (238, 237, 236, 241) that lack comfortable conditions for active transportation without added safety treatments.
• County roads (140, 141, 135) with higher traffic volumes and insufficient shoulder space for pedestrians and bicyclists.
»Environmental barriers, including the Salt River and surrounding wetlands, which limit feasible crossing locations and restrict east–west movement.
» Gaps near school walking routes, where missing sidewalks and inadequate crossings reduce safe access for students within typical walking and biking distances.
» Discontinuous network connectivity, particularly along on US-89 where the existing sidewalk and paved path dead end on the outskirts of Afton
These barriers informed the location of proposed paths, shoulder improvements, and crossings shown in Chapter 4.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
22
Across all elements of the existing conditions analysis—land use, population, crash data, origins/destinations, BLOS, and barriers/gaps—a single clear theme emerges:
The Upper Valley’s active transportation needs are corridor driven.
The most significant opportunities and challenges for walking, biking, and trail connectivity concentrate along a small number of key valley corridors, with US 89 as the spine that shapes nearly every mobility pattern in the region.
KEY FINDINGS & NEXT STEPS
Improvements to US-89 would have the biggest impact. Most of the population and destinations are along US-89. Connecting the communities of Auburn and Fairview to Afton would also provide value and may be easier to implement in some cases.
The current SRTS plan will complement and help with the prioritization of AT projects in the Upper Valley going forward, continuing the work of the 2012 Safe Routes to School Plan (SRTS) which has resulted in several AT projects being built.
Afton is the center of existing infrastructure—and the center of unmet demand.
Sidewalks, trails, crossings, and destinations are clustered within Afton, while
surrounding communities have no formal AT facilities. This creates natural “start–
end” points for future shared use paths and community connectors.
Barriers, gaps, and demand all line up geographically. The same locations where people need to walk/bike are where it is currently hardest or least safe to do so.
Corridor based planning will yield the highest value. This plan sets up a natural framework for prioritizing a handful of valley scale corridors and then planning local connections that feed into them.
EXISTING CONDITIONS
23
This page has been left intentionally blank.
UPPER VALLEY TRANSPORTATION ALTERNATIVES PLAN
24
03
COMMUNITY OUTREACH
Public involvement was a key component of the Upper Valley TAP. The project team used a combination of in-person outreach and an online survey to gather feedback from residents, identify transportation challenges, and understand community priorities for future walking and bicycling improvements. Outreach efforts included attendance at two community events, project details posted to the website throughout the study, and an online survey that was open throughout the planning process. Public input helped confirm the importance of school access, US-89 crossings, connections between Afton and nearby communities, and separated facilities on higher-speed roads.
The online survey was conducted to better understand existing walking and bicycling habits, identify barriers to active transportation, and gather community input on future improvements. The survey asked residents where they live, how frequently they walk or bicycle, the distances they travel, common destinations, reasons for walking and bicycling, and factors that limit their ability to do so. Participants were also asked about desired improvements, important destinations to connect, and their overall comfort level walking and bicycling in the Upper Valley.
A total of 173 residents completed the survey, representing communities throughout the Upper Valley. This response rate provides a statistically valid sample for the study area with a 95 percent confidence level and a 7.2 percent margin of error. Survey responses were received from residents in Afton, Fairview, Grover, Auburn, Osmond, Smoot, and surrounding areas, providing broad geographic representation across the valley.
PUBLIC SURVEY
SURVEY FINDINGS
173 SURVEY RESPONSES RECEIVED
87%SUPPORT BETTER WALKING & BIKING CONNECTIONS
Respondents indicated they would like
better trail, sidewalk, and pathway
connections between communities.
72%
WALK OR BIKE AT LEAST WEEKLY
Respondents are averaging 4.8 miles of
walking and biking per week.
Recreation and exercise were the primary reasons residents walk and bicycle - demonstrating the importance of active transportation facilities for both transportation and quality of life.
Residents emphasized the need for safer routes for children traveling to schools and recreational destinations, particularly in areas with narrow shoulders, high traffic speeds, and limited pedestrian facilities.
The most frequently identified barriers were the lack of sidewalks, trails, and bike lanes, along with safety concerns related to traffic speeds, roadway conditions, and limited separation from vehicles.
The first public outreach event was held during the Afton Oktoberfest in October 2025. Rather than hosting a standalone public meeting, the project team elected to participate in an established community event to maximize visibility and engage residents in a familiar setting. Project information, maps, and displays were provided at a staffed booth where community members could discuss transportation needs and share ideas for improving walking and bicycling throughout the Upper Valley.
Several recurring themes emerged from conversations with residents, including:
» The need for sidewalks and safer walking routes along Warrior Way serving the middle school and high school
» Interest in a regional pathway connection to Bedford and Thayne
» Support for a long-distance trail connection between Smoot and Alpine
» Improved sidewalk connectivity and pedestrian access within downtown Afton
Residents were also encouraged to participate in the project survey and provide more detailed feedback regarding potential projects and priorities.
The final public outreach event was held during a Star Valley High School track meet in May 2026. Similar to the Oktoberfest outreach effort, the project team engaged residents where they were already gathering and provided information about the plan, proposed projects, and next steps.
Feedback received at the event reinforced many of the themes identified through the survey process. Participants expressed strong overall support for the plan and recognized the value of creating safer walking and bicycling connections throughout the valley. School district representatives were supportive of efforts to improve connections to educational facilities and provide safer routes for students. Residents also asked questions regarding implementation timelines, funding opportunities, and project prioritization. Additional interest was expressed in improving connections in south Afton and extending active transportation opportunities to communities in the lower valley.
AFTON OKTOBERFEST
IN-PERSON OUTREACH
STAR VALLEY HIGH SCHOOL
TRACK MEET
Project information and feedback opportunity at Oktoberfest Project booth at the Star Valley High School track meet.
This page has been left intentionally blank.
04
CONCLUSION
The Upper Valley Transportation Alternatives
Plan (TAP) was developed to create a
connected, safe, and implementable active
transportation network that serves residents and
visitors throughout the valley. At the outset of
the planning process, stakeholders established
the following goals:
»Plan and prioritize a connected active transportation (AT) network
»Design safe and functional active
transportation facilities
»Enhance access to schools, neighborhoods, parks, businesses, and community destinations
»Develop realistic cost estimates
» Establish implementation priorities
Project recommendations were developed
through a combination of technical analysis,
community input, and stakeholder collaboration.
Key inputs included:
»Existing conditions analysis
»Review of previous plans and studies
»Bicycle Level of Service (BLOS) analysis
»Community survey results and
public outreach
»Stakeholder workshops and brainstorming sessions
The existing conditions analysis provided a
comprehensive understanding of transportation
conditions throughout the Upper Valley
and established the foundation for future
recommendations. The analysis included a
review of existing active transportation facilities,
previous planning efforts, land use patterns,
crash history, key origins and destinations,
HOW PROJECTS WERE DEVELOPED
FINAL RECOMMENDATIONS
bicycle comfort levels, and network barriers
and gaps. Together, these data sources helped
identify where active transportation investments
could provide the greatest benefit and where
constraints may affect implementation.
A Bicycle Level of Service (BLOS) analysis was completed to evaluate bicycling comfort and stress levels on roadways throughout the study area. Using traffic volumes, vehicle speeds, truck traffic, shoulder width, pavement condition, and other roadway characteristics, each roadway segment was assigned a comfort rating ranging from LOS A (low stress) to LOS F (high stress). The analysis identified corridors where high travel speeds, narrow or nonexistent shoulders, heavy vehicle traffic, and poor pavement conditions create significant barriers to bicycling. These findings helped guide project development by identifying locations where improvements such as shared-use paths, paved shoulders, roadway crossings, and pavement upgrades could provide the greatest benefit to bicyclist safety, comfort, and network connectivity.
Community outreach and survey results
provided an important local perspective
throughout the planning process. Residents
identified the destinations they most frequently
travel to, locations where they would like to walk
or bicycle more often, and barriers that currently
limit active transportation. This feedback helped
validate technical findings and ensure that
project recommendations reflected community
priorities and local travel patterns.
Together, these efforts helped identify the corridors, destinations, and network connections that would provide the greatest benefit for walking and bicycling throughout the Upper Valley.
Identify Need
Engage Public & Stakeholders
Prioritize Corridors
Recommend Routes & Improvements
Design concepts
Estimate Project Costs
Develop path To Implementation
!
PROJECT RECOMMENDATIONS
The recommended active transportation network
represents a long-term vision for improving walking and
bicycling throughout the Upper Valley. The network
consists of approximately 83 miles of improvements,
including 51 miles of shared-use pathways and 32 miles
of roadway shoulder improvements. Together, these
facilities create a connected system linking communities,
schools, parks, businesses, recreational destinations,
and other key community assets throughout the valley.
Figure 4.2. Proposed AT Projects for the Upper Valley
Stakeholders Brainstorm Project Ideas
RECOMMENDATIONS AIM TO:
»Connect active transportation (AT) network
»Improve safety and functionality of active transportation facilities
»Enhance access to schools, neighborhoods, parks, businesses, and community destinations.
»Develop realistic cost estimates
»Prioritize implementation and funding readiness
CROSSING RECOMMENDATIONS
Safe roadway crossings are a critical component of a connected active transportation network. Through stakeholder discussions and public input, 11 crosswalk locations and 5 underpass locations were identified for future consideration. Most of these recommendations are located within or near Afton, where pedestrian activity and destination density are highest. Additional priority crossings were identified in Smoot and Grover, where improved crossings of US-89 would enhance safety and connectivity for residents.
Safe Routes to School planning was conducted concurrently with this effort for each of the five schools in the Upper Valley. Those plans identify additional crossing improvements, sidewalk connections, and safety enhancements that complement the recommendations contained in this plan. Individual Safe Routes to School plans can be accessed at uppervalleytap.com.
Figure 4.3. Proposed Crossings and Underpasses
CONCEPT DESIGNS AND COST ESTIMATES
While all recommended projects contribute to the long-term vision of a connected active transportation network, certain projects emerged as higher priorities based on stakeholder input, community survey feedback, safety needs, network connectivity, and implementation feasibility.
To advance these priority projects beyond the planning stage, concept-level engineering and planning-level cost estimates were developed for approximately 16 miles of active transportation improvements and two key crossing locations. These projects generally represent corridors where improvements would provide significant connectivity benefits, address documented barriers, improve access to important destinations, or build upon existing infrastructure.
The development of concept-level designs does not imply that other recommended projects are less important. Rather, these projects were selected to provide a starting point for future funding applications, environmental review, right-of-way evaluation, and design development. As funding opportunities become available, these projects may be positioned for earlier implementation; however, all recommended projects remain important components of the overall network and should be pursued as resources allow. Additional details for each of the concept projects can be found in appendix A.
ID NAME LOCATION MILES COST EST.
1 Afton to Grover US 89 (Co Rd 136 to Co Rd 172)3.0 $4,500,000
2 Kennington-Burton Kennington-Burton Lane (US 89 to Co Rd 135)1.0 $2,060,000
3 Warrior Way Warrior Way (Co Rd 137 to Co Rd 136)1.1 $2,440,000
4 Swift Creek Ln Co Rd 137 (Warrior Way to Co Rd 135)0.5 $980,000
5 Alred Rd (North)Co Rd 135 (WY 238 to Co Rd 136)2.0 $3,600,000
6 Alred Rd (South)Co Rd 198 (WY 236 to WY 238)2.0 $2,300,000
7 Osmond to Fairview WY 236 (WY 241 to Co Rd 144)2.8 $5,600,000
8 Osmond to Smoot WY 241 (WY 236 to Co Rd 148) Dry Creek Rd (US 89 to WY 241)3.9 $5,300,000
9 Swift Creek Ln US 89 & Swift Creek Ln - $32,000
10 Osmond Elementary WY 241 & Co Rd 146 - $90,000
Figure 4.4. Concept Design Projects Map & Table
*Costs are planning-level estimate of probable cost based on current assumptions and should be
updated during survey, environmental review, right-of-way verification, utility review, and 30% design.
The Upper Valley Transportation Alternatives Plan is intended to serve as an implementation tool, not just a planning document. The recommended network, concept layouts, planning-level cost estimates, Safe Routes to School plans, survey results, and project website should be used together to help Lincoln County, local communities, WYDOT, the school district, and other partners move priority projects toward funding, design, and construction. The concept projects provide a starting point for grant applications and future project development, while the broader recommended network establishes the long-term vision for improving walking and bicycling throughout the Upper Valley.
The following funding strategy table provides a general framework for moving different types of projects forward. Funding sources and eligibility requirements may change over time, so project sponsors should confirm current program requirements before applying.
IMPLEMENTATION & FUNDING STRATEGY
The final deliverables from this plan should be used in different ways. The final report documents the need, process, public support, and recommended network. The concept layouts and cost estimates provide the technical foundation for funding applications and future design. The Safe Routes to School plans identify school-specific safety needs and can support near-term crossing, sidewalk, and access improvements.
Implementation will require continued coordination, local leadership, and opportunistic funding. No single funding source is likely to deliver the full recommended network at once. Instead, the plan should be advanced through a combination of early action projects, phased capital improvements, coordination with roadway projects, grant applications, and long-term partnerships. By using the plan as a shared roadmap, Upper Valley communities can steadily advance projects that improve safety, expand mobility choices, and create a more connected active transportation system over time.Figure 4.5. Funding Strategies
PROJECT TYPE LIKELY TO LEAD PARTNERS POTENTIAL FUNDING
School Crossings Town/County/ School District WYDOT SRTS, TAP, local funds
Shared-Use Paths on State Routes County/WYDOT Towns, School District TAP, FLAP, SS4A, RTP
County Road Pathways County Adjacent landowners TAP, local match, grants
Shoulder Widening County/WYDOT Towns STIP, safety funds, local capital
Underpasses WYDOT/County Towns, schools Federal discretionary grants, TAP, safety grants
APPENDICES
APPENDIX A - PROJECT CONCEPTS
APPENDIX B - COST ESTIMATES
APPENDIX C - INTERSECTION DESIGNS
APPENDIX D - CONCEPT LAYOUTS
This page has been left intentionally blank.
A
APPENDIX -
PROJECT CONCEPTS
PROJECT #1: AFTON TO GROVER TRAIL CONCEPT
Location: US 89 (Co Rd 136 to Co Rd 172)
Length: approx. 3 miles
Concept Facility: 10’ separated asphalt trail
This project consists of approximately 3 miles of 10’ separated asphalt trail. The concept trail location is on the east side of the right-of-way. Separation from the roadway will be achieved via swale/landscaped buffer of varied width with the trail and swale tapering on the south end to meet the existing sidewalk.
FHWA standards require minimum separation
from vehicular traffic according to vehicular
speed as listed:
»Vehicle Speeds 45 mph to 55 mph – 10’-20’ minimum separation
»Vehicle Speeds 60+ mph – 20’
minimum separation
»When separation is not possible, vehicle barriers can be utilized instead. These barriers are defined as Jersey Barriers, Guardrails, or Raised Grade Separation at a 1V:3H vertical-to-horizontal ratio. Striping or curb and gutter are not considered separation.
For estimation purposes 15’ minimum was
assumed for the swale adjacent to the existing
roadway. The concept level trail section design
assumption is for 3” Hot Mix Asphalt (HMA), 6”
Untreated Base Course (UTBC), and 12” Pit Run
Aggregate. Grading of the existing undeveloped
right-of-way may include some additional fill to
level the existing ground in preparation for the
trail improvements. No change to the existing
roadway pavement is anticipated for this trail.
The concept plan aimed to identify the existing driveways in the concept layouts. For the purpose of applying a preliminary cost to address driveway crossings, we have assumed typical driveway dimensions and thicknesses. In addition, it was assumed that each driveway would include a culvert through the swale which was assumed to be a 12” PVC or HDPE pipe with UTBC backfill.
»Residential Driveway: 24’ across by 20’ deep
with 6” concrete and 6” UTBC
»Commercial Driveway: 30’ across by 20’ deep with 6” concrete and 6” UTBC
As WYDOT owns this right-of-way cooperation with WYDOT engineers for the final design and construction is necessary.
PROJECT #2: KENNINGTON-BURTON LN TRAIL CONCEPT
Location: Kennington-Burton: WY 136A (US 89 to Co Rd 135)
Length: approx. 1.1 miles
Concept Facility: 10’ separated asphalt trail
This project consists of a 10’ separated asphalt
trail on the north side of Kennington-Burton Ln
from US-89 to Co Rd 135 (Allred Rd).
The concept level trail section design assumption is for 3” HMA, 6” UTBC, and 12” Pit Run Aggregate. Grading of the existing undeveloped right-of-way may include some additional fill to level the existing ground in preparation for the trail improvements.
SPECIAL CONSIDERATIONS ON KENNINGTON-BURTON LN TRAIL:
A crossing at Warrior Way was not included in
the concept, but consideration for a crossing
is recommended with the proposed middle
school access improvements on Kennington-
Burton Ln. Finally, the concept plan includes a
section of concrete sidewalk/trail to connect
the existing sidewalk on US-89 through the NW
corner property at the intersection of US-89
and Kennington-Burton Ln. Due to the existing
travel patterns observed onsite at the northwest
corner property of US-89 & Kennington-Burton
Ln, we anticipate that if asphalt trail were
installed it would experience unusually high
wear and tear. The edging and surface would
likely be damaged by vehicles crossing over the
trail in several places. It is recommended that
a concrete sidewalk expanding from 5’ at the
US-89 ADA ramp to 10’ at the connecting trail
along with curb and gutter and defined driveway
aprons be installed to limit vehicular movement
to appropriate distances from the intersection
and provide visibility for pedestrians.
PROJECT #3: WARRIOR WAY TRAIL CONCEPT
Location: Warrior Way (Co Rd 137 to Co Rd 136)
Length: approx. 1.1 miles
Concept Facility: 12’ separated concrete trail
with limited on-street parking
This project consists of a 12’ concrete trail located on the west side of Warrior Way from Swift Creek Ln to Rulon Gardner Rd and on the east side from Rulon Gardner Rd to Kennington-Burton Ln. In addition, on street parallel parking from Rulon Gardner Rd to the Star Valley Middle School property was desired for event parking at both the high school and middle school. This has been included in the concept plan.
ADA ramps were planned at the high school property to integrate the trail with existing improvements including curb and gutter and sidewalk. Separation of the trail at the stadium parking lot is encouraged. This plan assumed curbing or curb and gutter would be used to separate the roadway and parking lot from the trail. On-street parking was not included through the high school property. The Town of Afton may want to consider installing parking on the west side of the roadway with future development.
At the middle school the trail was adjusted to fit between the roadway and the parking lot. Separation of the trail and parking lot through curbing is recommended to prevent vehicles from driving across the trail to access the roadway. Due to limited space available at the middle school property, parking was eliminated and the swale width varies. A small section of on-street parking is shown north of the middle school parking lot; however, this section of parking may be eliminated during final design since the middle school may be implementing some access improvements on their property to Kennington-Burton Ln that may impact this area.
The Town of Afton is coordinating efforts for
the crossing and trail through the property on the east side of Warrior Way and north of Rulon Gardner Rd. Adjustments to the concept layout are expected during the design phase to coordinate the remaining trail with the development plans and installed infrastructure.
PROJECT #4: SWIFT CREEK LN TRAIL CONCEPT
Location: Swift Creek Ln: Co Rd 137
(Warrior Way to Co Rd 135)
Length: approx. 0.5 mile
Concept Facility: 10’ separated asphalt trail
This project consists of a separated 10’ asphalt trail on the south side of Swift Creek Ln from Warrior Way to Co Rd 135 (Allred Rd). The concept level trail section design assumption is for 3” HMA, 6” UTBC, and 12” Pit Run Aggregate. Grading of the existing undeveloped right-of-way may include some additional fill to level the existing ground in preparation for the trail improvements.
SPECIAL CONSIDERATIONS FOR SWIFT CREEK LN TRAIL:
The best location for the trail along Swift Creek Ln was not clearly apparent when reviewing the available contours, above ground utilities, and visiting the site. Both north and south sides have some overhead power, and the south side appears to have buried communication lines. Each side will likely require additional fill for grading and may require slope easements. In addition, the north side appears to have an irrigation ditch and a stretch of mature trees directly adjacent to the existing roadway pavement that would need to be piped and removed, respectively. For these reasons the concept layout was placed on the south side of Swift Creek Ln.
Due to the constraints found on-site and limited scope of this plan, additional investigation is strongly recommended. Performing 30% level design(s) is recommended prior to application for any funding that would include construction so that the final layout, or if another facility option might work better, can be determined. This is likely to be an iterative process since there are competing constraints on either side
of the roadway and more information along with associated costs may sway the final layout. The County may find that installing curb and gutter and a wider sidewalk may provide a better cost/benefit ratio than a separated trail for this area when the on-site constraints have been investigated further.
PROJECT #5: ALLRED RD (NORTH) TRAIL CONCEPT
Location: Allred Road: Co Rd 135
(WY 238 to Co Rd 136)
Length: approx. 2 miles
Concept Facility: 10’ separated asphalt trail
This project consists of a 10’ separated asphalt
trail located on the west side of Allred Rd. The
concept level trail section design assumption is
for 3” HMA, 6” UTBC, and 12” Pit Run Aggregate.
Grading of the existing undeveloped right-of-
way may include some additional fill to level
the existing ground in preparation for the trail
improvements.
The concept plan aimed to identify the existing driveways in the concept layouts. For the purpose of applying a preliminary cost to address driveway crossings, we have assumed typical driveway dimensions and thicknesses. In addition, it was assumed that each driveway would include a culvert through the swale which was assumed to be a 12” PVC or HDPE pipe with UTBC backfill.
»Residential Driveway: 24’ across by 20’ deep
with 6” concrete and 6” UTBC
»Commercial Driveway: 30’ across by 20’ deep with 6” concrete and 6” UTBC
Special consideration for this project includes
a water crossing at Swift Creek that will likely
require additional permitting. Permitting
requirements should be determined during
design. Preliminary costs have not factored
in any cost associated with permitting and
additional design / river modeling that might be
necessary. The concept plan assumed culvert
extensions would be used for all water crossings
with the installation of two 10’ box culverts for
the large crossings and 36” PVC/HDPE pipe for
smaller irrigation crossings.
In addition, there is one property that has an unconventional driveway that appears to be for loading livestock. Special coordination with this
property owner during design is recommended. Finally, additional fill material is likely to be needed to bring the proposed trail up to grade. This may involve adjustments to fences. Coordination with homeowners should be done during the design and construction phases.
PROJECT #6: ALLRED RD (SOUTH) TRAIL CONCEPT
Location: Allred Rd: Co. Rd 198
(WY 236 to WY 238)
Length: approx. 2 miles
Concept Facility: 10’ separated asphalt trail
This project consists of a 10’ separated asphalt
trail located on the west side of Allred Rd. The
concept level trail section design assumption
is for 3” HMA, 6” UTBC, and 12” Pit Run
Aggregate. Grading of the existing undeveloped
right-of-way may include some additional fill to
level the existing ground in preparation for the
trail improvements. No change to the existing
roadway pavement is anticipated for this trail.
The concept plan aimed to identify the existing driveways in the concept layouts. For the purpose of applying a preliminary cost to address driveway crossings, we have assumed typical driveway dimensions and thicknesses. In addition, it was assumed that each driveway would include a culvert through the swale which was assumed to be a 12” PVC or HDPE pipe with UTBC backfill.
»Residential Driveway: 24’ across by 20’ deep
with 6” concrete and 6” UTBC
»Commercial Driveway: 30’ across by 20’ deep with 6” concrete and 6” UTBC
Some additional fill may be required to bring the
proposed trail up to grade.
PROJECT #7: OSMOND TO FAIRVIEW TRAIL CONCEPT
Location: WY 236 (WY 241 to Co Rd 144)
Length: approx. 2.8 miles
Concept Facility: 12’ separated asphalt trail
with guardrail
This project consists of a 12’ separated asphalt trail with guardrail on the south side of Hwy 236. This roadway is utilized by the school district for school children to travel from Osmond Elementary to the parks in Fairview. The concept facility cross section was chosen based on a few factors. FHWA standards require minimum separation from vehicular traffic according to vehicular speed as shown:
»Vehicle Speeds 45 mph to 55 mph – 10-20 ft minimum separation
»Vehicle Speeds 60+ mph – 20 ft minimum separation
»When separation is not possible, vehicle barriers can be utilized instead. These barriers are defined as Jersey Barriers, Guardrails, or Raised Grade Separation at 1:3. Striping or curb and gutter are not considered separation.
Due to the posted speed limit of 55 mph and limited right-of-way along this roadway, a barrier was recommended. The concept proposed a guardrail, but jersey barriers would also be an acceptable option. An additional 2’ of trail width was included compared to the 10’ asphalt trails to provide additional room for trail users to navigate the trail, passing each other and providing space away from the guardrail and fast-moving vehicles. As WYDOT owns this right-of-way cooperation with WYDOT engineers for the final design and construction is necessary.
The concept level trail section design assumption is for 3” HMA, 6” UTBC, and 12” Pit Run Aggregate. Grading of the existing undeveloped right-of-way will include some additional fill to level the existing ground in preparation for the trail improvements. Only limited changes to the existing roadway pavement are anticipated to clean up the edge of pavement and install the separation.
Additional fill is likely to be needed to bring the proposed trail up to grade. Grading easements may be necessary in areas where additional fill is required and should be identified during the final design.
The concept plan aimed to identify the existing driveways in the concept layouts. For the purpose of applying a preliminary cost to address driveway crossings, we have assumed typical driveway dimensions and thicknesses. In addition, it was assumed that each driveway would include a culvert through the swale which was assumed to be a 12” PVC or HDPE pipe with UTBC backfill.
»Residential Driveway: 24’ across by 20’ deep with 6” concrete and 6” UTBC
»Commercial Driveway: 30’ across by 20’ deep with 6” concrete and 6” UTBC
Finally, there is a water crossing at Salt River that will likely require additional permitting. Permitting requirements should be determined during design. Preliminary costs have not factored in any cost associated with permitting and additional design / river modeling that might be necessary. The concept plan assumed culvert extensions would be used for all water crossings with installation of two 10’ box culverts for the large crossings and 36” PVC/HDPE pipe for smaller irrigation crossings.
CONCEPT PROJECT #8: SMOOT TO OSMOND TRAIL CONCEPT
Location: WY 241 (WY 236 to Co Rd 148 Dry Creek Rd (US 89 to WY 241)
Length: approx. 3.9 miles
Concept Facility: 10’ separated asphalt trail
This project consists of a 10’ separated asphalt
trail on the west side of WY 241 and on the
south side of Dry Creek Rd. Separation from the
roadway is achieved via a swale. For the trail on
WY 241 the swale is shown with varied width
that expands to a wider width at the south end
of the trail due to the increased speeds and
required separation by FHWA standards. The
basic concept cross sections assume a right-of-
way width for all roadways of 60’; however, it is
likely that this roadway has additional right-of-
way available since it is a state road. Verification
of right-of-way should be determined via survey
in the full design of the trail. No additional costs
were included for right-of-way purchase in the
concept plan. If additional right-of-way beyond
60’ is not available, a barrier may be required in
the final design. As WYDOT owns this right-of-
way cooperation with WYDOT engineers for the
final design and construction is necessary.
The concept plan aimed to identify the existing driveways in the concept layouts. For the purpose of applying a preliminary cost to address driveway crossings, we have assumed typical driveway dimensions and thicknesses. In addition, it was assumed that each driveway would include a culvert through the swale which was assumed to be a 12” PVC or HDPE pipe with UTBC backfill.
»Residential Driveway: 24’ across by 20’ deep
with 6” concrete and 6” UTBC
»Commercial Driveway: 30’ across by 20’ deep with 6” concrete and 6” UTBC
In addition, there is a water crossing at
Dry Creek that will likely require additional
permitting. Permitting requirements should
be determined during design. Preliminary costs have not factored in any cost associated with permitting and additional design / river modeling that might be necessary. The concept plan assumed culvert extensions would be used for all water crossings with installation of two 10’ box culverts for the large crossings and 36” PVC/HDPE pipe for smaller irrigation crossings.
PROJECT #9: US – 89 AT
SWIFT CREEK LN CROSSWALK
CONCEPT
This project comprises the installation of a zebra
style crosswalk at the intersection of US – 89
and Swift Creek Lane. Work includes installation
of advanced warning and crossing signage, a
zebra style crosswalk striping and installation of
an inline ADA ramp on the east side of US – 89.
This crosswalk will provide increased visibility
for pedestrians, including students at Star Valley
High School and Star Valley Middle School.
Consultant engineers recommend flag stations be included on the crossing signage posts to allow for increased visibility of pedestrians while crossing. Future consideration of additional intersection improvements is recommended, such as installing a HAWK signal at the crossing or fully signalizing the intersection with any future buildout of an eastern roadway in alignment with Swift Creek Lane.
PROJECT #10: OSMOND
ELEMENTARY SCHOOL
CROSSWALK WITH
RECTANGULAR RAPID
FLASHING BEACONS (RRFB)
This project consists of the installation of zebra style crosswalks on the west and south legs of the intersection of WY 241 and Co Rd 146. The project includes advance warning and crosswalk signage for both crosswalks, zebra style roadway striping and crosswalk pavement markings on WY 241, an RRFB style crossing signal on each side for east west pedestrian traffic on WY 241, and sidewalk improvements to connect the proposed trail and Osmond Elementary School. Integrated solar power is anticipated for powering the RRFB. Solar options are available and can be specified during the design.
B
APPENDIX - COST ESTIMATES
This page has been left intentionally blank.
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Afton to Grover Project No.:
Date:
Location:US 89 (Co Rd 136 to Co Rd 172)Sheet:
Approx. 3 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 151,700.00$ 151,700$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 29,400.00$ 29,400$
4 Materials Sampling & Testing 1 LS 30,000.00$ 30,000$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 15,000.00$ 15,000$
7 Construction Staking 1 LS 20,000.00$ 20,000$
8 Clear and Grub 11 AC 25,000.00$ 263,800$
9 Excavation and Grading 25520 CY 18.00$ 459,400$
10 Pit Run Aggregate (trail)8213 CY 40.00$ 328,600$
11 Pit Run Aggregate (Grading Fill - 3' x 20') 17600 CY 40.00$ 704,000$
12 UTBC 4107 CY 90.00$ 369,700$
13 Asphalt (3" HMA PG 58-28)2911 TON 200.00$ 582,200$
14 Residential Concrete Driveway (24' x 20'; 6" thick, 6" UTBC)15 EA 6,000.00$ 90,000$
15 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)6 EA 8,750.00$ 52,500$
16 Driveway Culvert (12" PVC or HDPE with UTBC backfill/honching)21 EA 4,000.00$ 84,000$
17 Water Crossing (Culvert Extension)1 EA 15,000.00$ 15,000$
SUBTOTAL 3,199,000$
18 Construction Contingency (15% Construction Cost)1 L.S. 479,900$ 479,900$
CONSTRUCTION TOTAL 3,679,000$
19 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 367,900$ 367,900$
20 Construction Administration (10% Construction Cost)1 L.S. 367,900$ 367,900$
21 Legal & Fiscal 1 L.S.5,000$ 5,000$
TOTAL COST 4,500,000$
KS
Preliminary Opinion of Probable Cost
1
6/10/2026
1 of 1
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Kennington-Burton Trail Improvements Project No.:
Date:
Location:WY 236 (US 89 to Co Rd 135)Sheet:
Approx. 1.1 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 134,900.00$ 134,900$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 12,900.00$ 12,900$
4 Materials Sampling & Testing 1 LS 19,400.00$ 19,400$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 10,000.00$ 10,000$
7 Construction Staking 1 LS 13,000.00$ 13,000$
8 Sawcut Existing Asphalt 5808 LF 1.00$ 5,808$
9 Removal of Bituminous Surface 3872 SY 5.00$ 19,360$
10 Clear and Grub 2.4 AC 25,000.00$ 60,000$
11 Excavation and Grading 5808 CY 18.00$ 104,544$
12 Pit Run Aggregate (roadway/trail)3012 CY 40.00$ 120,480$
13 Pit Run Aggregate (Grading Fill - 3' x 20') 11733 CY 40.00$ 469,320$
14 UTBC 1506 CY 90.00$ 135,540$
15 Asphalt (3" HMA PG 58-28)1067 TON 200.00$ 213,400$
16 10' Concrete Sidewalk (4" Thick ; 6" UTBC)170 LF 90.00$ 15,300$
17 Concrete Curb & Gutter 170 LF 90.00$ 15,300$
18 Residential Concrete Driveway (24' x 20'; 6" thick, 6" UTBC)9 EA 6,000.00$ 54,000$
19 Driveway Culvert (12" PVC or HDPE with UTBC backfill/honching)9 EA 4,000.00$ 36,000$
20 Water Crossing (Culvert Extension)2 EA 15,000.00$ 30,000$
21 Centerline Striping 5808 LF 0.60$ 3,485$
22 Fog Line Striping 11616 LF 0.60$ 6,970$
SUBTOTAL 1,484,000$
23 Construction Contingency (15% Construction Cost)1 L.S.222,600$ 222,600$
CONSTRUCTION TOTAL 1,707,000$
24 Engineering Design & Bidding (10% Construction Cost)1 L.S.170,700$ 170,700$
25 Construction Administration (10% Construction Cost)1 L.S.170,700$ 170,700$
26 Legal & Fiscal 1 L.S.5,000$ 5,000$
TOTAL COST 2,060,000$
Preliminary Opinion of Probable Cost
2
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Warrior Way Trail Improvements Project No.:
Date:
Location:Warrior Way (Co Rd 137 to Co Rd 136)Sheet:
Approx. 1.1 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 163,000.00$ 163,000$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 31,000.00$ 31,000$
4 Materials Sampling & Testing 1 LS 23,300.00$ 23,300$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 10,000.00$ 10,000$
7 Construction Staking 1 LS 12,000.00$ 12,000$
8 Sawcut Existing Asphalt 3960 LF 1.00$ 4,000$
9 Clear and Grub 3.60 AC 25,000.00$ 90,000$
10 Excavation and Grading 10560 CY 18.00$ 190,100$
11 Pit Run Aggregate (roadway/trail)4058 CY 40.00$ 162,400$
12 Pit Run Aggregate (Grading Fill - 3' x 20') 1408 CY 40.00$ 56,400$
13 UTBC 2029 CY 90.00$ 182,700$
14 Asphalt (3" HMA PG 58-28)655 TON 200.00$ 131,000$
15 12' Concrete Trail (6" thick)5280 LF 120.00$ 633,600$
16 5' Concrete Sidewalk (4" Thick ; 6" UTBC)62 LF 50.00$ 3,100$
17 ADA Ramp 5 EA 4,000.00$ 20,000$
18 Concrete Curb & Gutter 750 LF 90.00$ 67,500$
19 Centerline Striping 5280 LF 0.60$ 3,200$
20 Fog Line Striping 5280 LF 0.60$ 3,200$
21 Parking Striping 2933 LF 0.90$ 2,700$
22 Zebra Crosswalk 40 LF 60.00$ 2,400$
23 Advanced Warning / Crosswalk Signage 2 EA 2,000.00$ 4,000$
SUBTOTAL (rounded)1,800,000$
24 Construction Contingency (15% Construction Cost)1 L.S. 270,000$ 270,000$
CONSTRUCTION TOTAL (rounded)2,070,000$
25 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 180,000$ 180,000$
26 Construction Administration (10% Construction Cost)1 L.S. 180,000$ 180,000$
27 Legal & Fiscal 1 L.S.5,000$ 5,000$
TOTAL COST (rounded)2,440,000$
KS
Preliminary Opinion of Probable Cost
3
6/10/2026
1 of 1
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Swift Creek Ln Project No.:
Date:
Location:Co Rd 137 (Warrier Way to Co Rd 135) Sheet:
Approx. 0.5 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 63,700.00$ 63,700$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 6,100.00$ 6,100$
4 Materials Sampling & Testing 1 LS 9,100.00$ 9,100$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 6,100.00$ 6,100$
7 Construction Staking 1 LS 10,000.00$ 10,000$
8 Sawcut Existing Asphalt 2640 LF 1.00$ 2,640$
9 Removal of Bituminous Surface 1760 SY 5.00$ 8,800$
10 Clear and Grub 1 AC 25,000.00$ 27,250$
11 Excavation and Grading 2640 CY 18.00$ 47,520$
12 Pit Run Aggregate (roadway/trail)1369 CY 40.00$ 54,760$
13 Pit Run Aggregate (Grading Fill - 3' x 20') 5866.50 CY 40.00$ 234,660$
14 UTBC 684 CY 90.00$ 61,560$
15 Asphalt (3" HMA PG 58-28)485 TON 200.00$ 97,000$
16 Residential Concrete Driveway (24' x 20'; 6" thick, 6" UTBC)5 EA 6,000.00$ 30,000$
17 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)1 EA 8,750.00$ 8,750$
18 Driveway Culvert (12" PVC or HDPE with UTBC backfill/honching)6 EA 4,000.00$ 24,000$
19 Centerline Striping 2640 LF 0.60$ 1,584$
20 Fog Line Striping 5280 LF 0.60$ 3,168$
SUBTOTAL 701,000$
21 Construction Contingency (15% Construction Cost) 1 L.S. 105,200$ 105,200$
CONSTRUCTION TOTAL 807,000$
22 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 80,700$ 80,700$
23 Construction Administration (10% Construction Cost) 1 L.S. 80,700$ 80,700$
24 Legal & Fiscal 1 L.S. 5,000$ 5,000$
TOTAL COST 980,000$
Preliminary Opinion of Probable Cost
4
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Allred Road (North) Trail Improvement Project No.:
Date:
Location:Co Rd 135 (WY 238 to Co Rd 136)Sheet:
Approx. 2 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 235,700.00$ 235,700$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 22,800.00$ 22,800$
4 Materials Sampling & Testing 1 LS 25,000.00$ 25,000$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 12,500.00$ 12,500$
7 Construction Staking 1 LS 17,500.00$ 17,500$
8 Sawcut Existing Asphalt 10560 LF 1.00$ 10,600$
9 Removal of Bituminous Surface 7040 SY 5.00$ 35,200$
10 Clear and Grub 4 AC 25,000.00$ 109,000$
11 Excavation and Grading 10560 CY 18.00$ 190,100$
12 Pit Run Aggregate (roadway/trail)5476 CY 40.00$ 219,100$
13 Pit Run Aggregate (Grading Fill - 3' x 20') 11733 CY 40.00$ 469,400$
14 UTBC 2738 CY 90.00$ 246,500$
15 Asphalt (3" HMA PG 58-28)1940 TON 200.00$ 388,000$
16 Residential Concrete Driveway (24' x 20'; 6" thick, 6" UTBC)28 EA 6,000.00$ 168,000$
17 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)7 EA 8,750.00$ 61,300$
18 Driveway Culvert (12" PVC or HDPE with UTBC backfill/honching)35 EA 4,000.00$ 140,000$
19 Water Crossing (Culvert Extension)2 EA 15,000.00$ 30,000$
20 Water Crossing (Box Culvert)1 EA 195,000.00$ 195,000$
21 Centerline Striping 10560 LF 0.60$ 6,400$
22 Fog Line Striping 10560 LF 0.60$ 6,400$
SUBTOTAL 2,600,000$
23 Construction Contingency (15% Construction Cost) 1 L.S. 390,000$ 390,000$
CONSTRUCTION TOTAL 2,990,000$
24 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 260,000$ 260,000$
25 Construction Administration (10% Construction Cost) 1 L.S. 260,000$ 260,000$
26 Legal & Fiscal 1 L.S.5,000$ 5,000$
TOTAL COST 3,600,000$
Preliminary Opinion of Probable Cost
5
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Allred Road (South) Trail Improvement Project No.:
Date:
Location:Co. Rd 198 (WY 236 to WY 238)Sheet:
Approx. 2 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 149,100.00$ 149,100$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 14,300.00$ 14,300$
4 Materials Sampling & Testing 1 LS 21,400.00$ 21,400$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 12,500.00$ 12,500$
7 Construction Staking 1 LS 17,500.00$ 17,500$
8 Sawcut Existing Asphalt 10560 LF 1.00$ 10,600$
9 Removal of Bituminous Surface 7040 SY 5.00$ 35,200$
10 Clear and Grub 4 AC 25,000.00$ 109,000$
11 Excavation and Grading 10560 CY 18.00$ 190,100$
12 Pit Run Aggregate (roadway/trail)5476 CY 40.00$ 219,100$
13 Pit Run Aggregate (Grading Fill - 3' x 20') 2933 CY 40.00$ 117,400$
14 UTBC 2738 CY 90.00$ 246,500$
15 Asphalt (3" HMA PG 58-28)1940 TON 200.00$ 388,000$
16 Residential Concrete Driveway (24" x 20"; 6" thick, 6" UTBC)8 EA 6,000.00$ 48,000$
17 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)1 EA 8,750.00$ 8,800$
18 Driveway Culvert (12' PVC or HDPE with UTBC backfill/honching)9 EA 4,000.00$ 36,000$
19 Centerline Striping 10560 LF 0.60$ 6,400$
20 Fog Line Striping 10560 LF 0.60$ 6,400$
SUBTOTAL 1,640,000$
21 Construction Contingency (15% Construction Cost) 1 L.S. 246,000$ 246,000$
CONSTRUCTION TOTAL 1,890,000$
22 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 164,000$ 164,000$
23 Construction Administration (10% Construction Cost) 1 L.S. 164,000$ 164,000$
24 Legal & Fiscal 1 L.S. 5,000$ 5,000$
TOTAL COST 2,300,000$
Preliminary Opinion of Probable Cost
6
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Osmond to Fairview Project No.:
Date:
Location:WY 236 (WY 241 to Co Rd 144)Sheet:
approx. 2.8 miles By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 301,600.00$ 301,600$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 29,200.00$ 29,200$
4 Materials Sampling & Testing 1 LS 30,000.00$ 30,000$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 15,000.00$ 15,000$
7 Construction Staking 1 LS 25,000.00$ 25,000$
8 Sawcut Existing Asphalt 14784 LF 1.00$ 14,784$
9 Removal of Bituminous Surface 3285 SY 5.00$ 16,425$
10 Clear and Grub 5 AC 25,000.00$ 125,000$
11 Excavation and Grading 13141 CY 18.00$ 236,538$
12 Pit Run Aggregate (Grading Fill - 3' x 20') 16426 CY 40.00$ 657,048$
13 Pit Run Aggregate (roadway/trail)7118 CY 40.00$ 284,720$
14 UTBC 3559 CY 90.00$ 320,310$
15 Asphalt (3" HMA PG 58-28)3260 TON 200.00$ 652,000$
16 Residential Concrete Driveway (24" x 20"; 6" thick, 6" UTBC)28 EA 6,000.00$ 168,000$
17 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)7 EA 8,750.00$ 61,250$
18 Water Crossing (Pipe Culvert Extension)1 EA 15,000.00$ 15,000$
19 Water Crossing (Box Culvert)1 EA 195,000.00$ 195,000$
20 Driveway Culvert (12' PVC or HDPE with UTBC backfill/honching)35 EA 4,000.00$ 140,000$
21 Centerline Striping 14784 LF 0.60$ 8,870$
22 Fog Line Striping 29568 LF 0.60$ 17,741$
23 Guardrail 14784 LF 40.00$ 591,360$
SUBTOTAL 3,910,000$
24 Construction Contingency (15% Construction Cost) 1 L.S. 586,500$ 586,500$
CONSTRUCTION TOTAL 4,500,000$
25 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 450,000$ 450,000$
26 Construction Administration (10% Construction Cost) 1 L.S. 450,000$ 450,000$
27 Legal & Fiscal 1 L.S. 5,000$ 5,000$
28 Easement Contingency (10% Construction Cost)1 L.S. 150,000$ 150,000$
TOTAL COST 5,600,000$
Preliminary Opinion of Probable Cost
7
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Smoot To Osmond Project No.:
Date:
Location:WY 241 (WY 236 to Co Rd 148) &Sheet:
Dry Creek Rd (US 89 to WY 241)By:
approx. 3.9 miles
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 349,500.00$ 349,500$
2 Pre-Construction DVD 1 LS 500.00$ 500$
3 Traffic Control 1 LS 33,700.00$ 33,700$
4 Materials Sampling & Testing 1 LS 40,000.00$ 40,000$
5 Subsurface investigation 8 HR 400.00$ 3,200$
6 SWPPP 1 LS 20,000.00$ 20,000$
7 Construction Staking 1 LS 30,000.00$ 30,000$
8 Sawcut Existing Asphalt 20592 LF 1.00$ 20,600$
9 Removal of Bituminous Surface 13728 SY 5.00$ 68,700$
10 Clear and Grub 9 AC 25,000.00$ 212,800$
11 Excavation and Grading 20592 CY 18.00$ 370,700$
12 Pit Run Aggregate (Grading Fill) 1408 CY 40.00$ 56,400$
13 Pit Run Aggregate (roadway/trail)10677 CY 40.00$ 427,100$
14 UTBC 5339 CY 90.00$ 480,600$
15 Asphalt (3" HMA PG 58-28)3784 TON 200.00$ 756,800$
16 Residential Concrete Driveway (24' x 20'; 6" thick, 6" UTBC)55 EA 6,000.00$ 330,000$
17 Commercial Concrete Driveway (35' x 20'; 6" thick ; 6" UTBC)15 EA 8,750.00$ 131,300$
18 Driveway Culvert (12" PVC or HDPE with UTBC backfill/honching)70 EA 4,000.00$ 280,000$
19 Water Crossing (Box Culvert)1 EA 195,000.00$ 195,000$
20 Centerline Striping 20592 LF 0.60$ 12,400$
21 Fog Line Striping 41184 LF 0.60$ 24,800$
SUBTOTAL 3,850,000$
22 Construction Contingency (15% Construction Cost) 1 L.S. 577,500$ 577,500$
CONSTRUCTION TOTAL 4,430,000$
23 Engineering Design & Bidding (10% Construction Cost) 1 L.S. 385,000$ 385,000$
24 Construction Administration (10% Construction Cost) 1 L.S. 385,000$ 385,000$
25 Legal & Fiscal 1 L.S.5,000$ 5,000$
TOTAL COST 5,300,000$
Preliminary Opinion of Probable Cost
8
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: US HWY- 89 Crosswalk Improvement Project No.:
Date:
Location:US Hwy-89 and Swift Creek Ln Sheet:
By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 1,900.00$ 1,900$
2 Pre-Construction DVD 1 LS 200.00$ 200$
3 Traffic Control 1 LS 600.00$ 600$
4 Materials Sampling & Testing 1 LS 300.00$ 300$
5 Subsurface investigation 1 HR 400.00$ 400$
6 SWPPP 1 LS 200.00$ 200$
7 ADA Ramp (demo incidental to installation)1 EA 5,000.00$ 5,000$
8 Zebra Crosswalk Striping 65 LF 60.00$ 3,900$
9 Advanced Warning / Crosswalk Signage 4 EA 2,500.00$ 10,000$
SUBTOTAL 23,000$
10 Construction Contingency (15% Construction Cost) 1 L.S. 3,500$ 3,500$
CONSTRUCTION TOTAL 27,000$
11 Engineering Design (10% Construction Cost)1 L.S. 2,300$ 2,300$
12 Construction Administration (10% Construction Cost) 1 L.S. 2,300$ 2,300$
TOTAL COST 32,000$
Preliminary Opinion of Probable Cost
9
6/10/2026
1 of 1
KS
SUNRISE ENGINEERING, INC.
CONSULTING ENGINEERS AND SURVEYORS
Project: Osmond Elementary Crosswalk Improvement Project No.:
Date:
Location:WY 241 and Co Rd 146 Sheet:
By:
ITEM NO.ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization 1 LS 3,400.00$ 3,400$
2 Pre-Construction DVD 1 LS 200.00$ 200$
3 Traffic Control 1 LS 1,800.00$ 1,800$
4 Materials Sampling & Testing 1 LS 900.00$ 900$
5 Subsurface investigation 2 HR 400.00$ 800$
6 SWPPP 1 LS 600.00$ 600$
7 Construction Staking 1 LS 1,200.00$ 1,200$
8 Sawcut Existing Asphalt 25 LF 5.00$ 200$
9 Removal of Bituminous Surface 8 SY 40.00$ 400$
10 Excavation and Grading 30 CY 100.00$ 3,000$
11 5' Concrete Sidewalk (4" Thick ; 6" UTBC)170 LF 45.00$ 7,700$
12 ADA Ramp (6" UTBC incidental to installation)3 EA 4,000.00$ 12,000$
13 Zebra Crosswalk Striping 80 LF 60.00$ 4,800$
14 Advanced Warning / Crosswalk Signage 2 EA 2,500.00$ 5,000$
15 RRFB Crossing Signal (solar)2 EA 12,000.00$ 24,000$
SUBTOTAL 66,000$
16 Construction Contingency (15% Construction Cost) 1 L.S. 9,900$ 9,900$
CONSTRUCTION TOTAL 76,000$
17 Engineering Design (10% Construction Cost)1 L.S. 6,600$ 6,600$
18 Construction Administration (10% Construction Cost) 1 L.S. 6,600$ 6,600$
TOTAL COST 90,000$
Preliminary Opinion of Probable Cost
10
6/10/2026
1 of 1
KS
C
APPENDIX -
INTERSECTION DESIGNS
This page has been left intentionally blank.
X-INGX-INGSCHOOLSCHOOLX-INGX-INGSCHOOLSCHOOL169'260'50'32'8'8'12'5.9'±1.5'50'32'8'8'HALE LNHWY 89SWIFT CREEK LNwww.sunrise-eng.comENGINEERINGAFTON, WYOMING 83110770 S WASHINGTON STREET SUITE ATEL 307.885.8500 Z FAX 307.885.8501SCHOOL CROSSING AHEADSCHOOL CROSSINGLEGEND
SCHOOLX-INGSCHOOLX-INGDRY CREEK RDWYOMING HWY 2411.5'12'5.7'±6'±12'1.5'50'32'8'8'5'300'300'54'8'32'8'176'128'www.sunrise-eng.comENGINEERINGAFTON, WYOMING 83110770 S WASHINGTON STREET SUITE ATEL 307.885.8500 Z FAX 307.885.8501SCHOOL CROSSING AHEADSCHOOL CROSSINGPEDESTRIAN CROSSING AHEADPEDESTRIAN CROSSINGYIELD HERE TO PEDESTRIANSLEGEND
D
APPENDIX -
CONCEPT LAYOUTS
UPPER VALLEY TRANSPORTATION
ALTERNATIVES PLAN
Community Connectivity • Safety • Recreation • Mobility
WHY THIS PLAN MATTERS The plan provides a shared vision for creating safer, more connected walking and bicycling opportunities throughout the Upper Valley communities of Afton, Auburn, Fairview, Grover, Osmond, and Smoot.
THE CHALLENGE Most existing sidewalks, trails, and crossings are concentrated in Afton. US-89 is the region's primary corridor and a major safety and connectivity challenge. Approximately 500 crashes were reported between 2020 and 2024, with about 66% occurring along US-89.
WHAT RESIDENTS SAID 173 residents participated. 87% support improved walking and bicycling connections and 72% walk or bike at least weekly. Top priorities include safer routes to schools, better community connections, more pathways, and safer US-89 crossings.
THE RECOMMENDED NETWORK 51 miles of shared-use pathways and 32 miles of shoulder improvements are recommended, totaling 83 miles of new active transportation facilities. The plan also identifies 11 crosswalk locations and 5 potential underpasses.
PRIORITY PROJECTS Major projects include the Afton to Grover Trail, Warrior Way Trail, Kennington-Burton Trail, Allred Road Trails, Osmond to Fairview Trail, Smoot to Osmond Trail, and key crossing improvements. Estimated investment is approximately $27 million.
KEY TAKEAWAYS Focus investments on the US-89 corridor, connect communities, improve safety, and pursue state and federal grant funding opportunities.
VISION A safe, connected, and accessible active transportation network that improves quality of life, supports recreation and economic vitality, enhances school access, and links Upper Valley communities.
PRIORITY PROJECTS & ESTIMATED COSTS Project Estimated Cost Afton to Grover Trail $4.50 million Kennington-Burton Trail $2.06 million Warrior Way Trail $2.44 million Swift Creek Lane Trail $980,000 Allred Road North Trail $3.60 million Allred Road South Trail $2.30 million Osmond to Fairview Trail $5.60 million Smoot to Osmond Trail $5.30 million US-89 / Swift Creek Crosswalk $32,000 Osmond Elementary RRFB Crosswalk $90,000 Total estimated cost of priority projects: approximately $27 million.